Use the following information to answer parts

athrough
h. Describe what the

Question

Use the following information to answer parts athrough h. Describe what the

resus of each calculation mean to you as a project manager. What do you propose to do?

PV = $25,000

EV = $30,000

AC = $29,000

BAC = $1,000,000

a. Schedule variance (SV)

b. Cost variance (CV)

c. Schedule performance index (SPI)

d. Cost performance index (CPI)

e. Estimate to complete (ETC—first method)

f. Estimate to complete (ETC—second method)

g. Estimate at completion (EAC)

h. To-complete performance index (TCPI)

Project Management